Mock Exam Q1
Page 1 of 1
Mock Exam Q1
manickonline
December 2015 edited December 2015 in PM Certifications 0
You are in the planning process of a $1b project. You realize that your schedule requires more resources in certain months of the project than that are available to you. Your senior management has clearly instructed that you will not be able to obtain any additional resources for the project. So, you instruct your planner to adjust the schedule to accommodate these constraints. What are you instructing the planner to do?
1.Crashing
2.Resource leveling
3.Programme Evaluation and Review Technique
4.Fast tracking
Please provide your answer with justification. Justifying your answer with explanation helps you to remember the concept and also help others to understand. Thanks.
Regards,
Manick
PMP Lessons Learned
December 2015 edited December 2015 in PM Certifications 0
You are in the planning process of a $1b project. You realize that your schedule requires more resources in certain months of the project than that are available to you. Your senior management has clearly instructed that you will not be able to obtain any additional resources for the project. So, you instruct your planner to adjust the schedule to accommodate these constraints. What are you instructing the planner to do?
1.Crashing
2.Resource leveling
3.Programme Evaluation and Review Technique
4.Fast tracking
Please provide your answer with justification. Justifying your answer with explanation helps you to remember the concept and also help others to understand. Thanks.
Regards,
Manick
PMP Lessons Learned
Page 1 of 1
Permissions in this forum:
You cannot reply to topics in this forum